Subject: IMPORTANT INFORMATION: Upgrade on N1: WEF 15 FEB 2016
For your information, below is an extract from a report received via Transport for Cape Town.
These upgrades will be affecting all travelers using the N1 on specific sections wef mid February 2016.
We have been advised by the successful contactors (Mr Jared Smith from Martin & East) that the following is intended:
The scope of work on the N1: 3rd Lane Contract:
The specific objective of this, Western Cape Government Provincial Roads and Transport Management Project, is to improve the capacity and safe operating conditions of the TR9/1 between Plattekloof Road Interchange and the Stellenberg (R300) Interchange by :
· Constructing additional lanes on the carriageways of the freeway in order to improve traffic safety and capacity;
· Constructing new auxiliary lanes to improve weaving conditions;
· Extending the existing concrete median barrier to prevent head-on collisions;
· Constructing intersection improvements at various interchanges in order to improve traffic safety and capacity;
· Demolishing and reconstructing the Old Oak West Bridge, which has insufficient vertical clearance making it unsafe for heavy vehicles carrying high or abnormal loads; and
· Installing a new 1525 mm diameter water main along the southern boundary of the TR9/1 road reserve, so that the existing Wemmershoek Pipeline in the freeway median can be decommissioned.
The above mentioned project will commence mid to end February 2016 with an estimated duration of 36 months.
Traffic shall be accommodated on the existing surfaced carriageway and shoulders. Temporary deviations may be required at certain road junctions / intersections within the interchanges under this contract. Accommodation of traffic for rehabilitation work on the carriageways and ramps shall generally be carried out by closing off one lane of traffic at a time and accommodating the traffic on the other lane(s).
There shall be restricted working hours for any construction activities on the carriageways, ramps and crossing roads which negatively affect the traffic capacity during the peak periods. The restricted working hours for any operations which encroach onto the usable traffic lanes (excluding shoulders) shall be as follows:
· 06:00 to 09:00 on the inbound carriageway of TR9/1;
· 15:00 to 19:00 on the outbound carriageway of TR9/1;
· 06:00 to 09:00 on all ramps and crossing roads; and
· 15:00 to 19:00 on all ramps and crossing roads.
regards
Elizabeth (Elize) Jacobs
De Grendel Subcouncil (3)
Dept: Councillor Support and Subcouncils
Dir: Corporate Services and Compliance
Address: 1st Floor, Goodwood Municipal Building
261 Voortrekker Road
P Help save paper - do you really need to print this email ?
Disclaimer: This e-mail (including attachments) is subject to the disclaimer published at: http://www.capetown.gov.za/en/Pages/disclaimer.aspx. Please read the disclaimer before opening any attachment or taking any other action in terms of this e-mail. If you cannot access the disclaimer, kindly send an email to disclaimer@capetown.gov.za and a copy will be provided to you. By replying to this e-mail or opening any attachment you agree to be bound by the provisions of the disclaimer.